Spain faces an energy paradox: the same scenario that is deteriorating the profitability of photovoltaics is strengthening its capacity to attract data centers .
The increasing concentration of solar generation during the middle of the day has put pressure on wholesale prices, reduced the value captured by the plants, and increased competition among projects to close power purchase agreements.
This scenario represents an advantage for an industry whose viability depends, to a large extent, on guaranteeing large volumes of supply over long periods.
“When energy prices are low, it encourages consumption; when they are high, it encourages generation. Right now, we have a great opportunity to attract data centers,” says Jorge González-Onieva, business development director at Osprel, in an interview with Energía Estratégica .

The opportunity arises as Spanish electricity demand begins to recover, albeit gradually. During the first half of 2026, it reached 127,020 GWh , 1.4% more than in the same period of the previous year, while renewables contributed 58.4% of national generation in June.
“The market is still starting from a relatively small scale compared to the enormous volume of announced projects. At the end of 2025, Spain had 439 MW of installed IT capacity in commercial data centers, 24% more than the previous year. SpainDC estimates that this capacity could exceed 2,500 MW by 2030, although some of the announced pipeline may not necessarily be built.”
Data centers could accelerate this transformation of the consumption profile. However, cheap energy alone does not guarantee that projects will come to fruition : they need access capacity, land, connectivity, stable contracts, and administrative timelines compatible with an industry where being late can render an investment obsolete before it even opens.
From competing to supply energy to attracting demand
The change is already beginning to modify the strategy of independent energy producers.
“We have gone from having a huge volume of photovoltaic projects under development to only having projects that were under construction or had a signed PPA,” says González-Onieva.
“Many projects are competing to secure PPAs, and there has also been price cannibalization. For data centers, however, low energy prices are an incentive.”
The advantage of IPPs is not limited to the cost of generation.
Renewable energy developers have land, local relationships, technical studies, development teams and, especially, grid access positions that can acquire new value when combined with demand.
In certain cases, a position used to inject electricity can also serve as a point from which to request consumption capacity. Thus, an asset initially conceived as a generation plant can evolve into an integrated complex with renewable energy production, a data center, and grid backup.
“There have been major renewable energy players who were very agile and requested consumption capacity in generation positions for data center projects,” explains González-Onieva.
“That improves the value of their assets: they can increase demand at their node, have a self-consumption PPA with a data center, and even sell the access point and connection for on-demand use.”
The strategy allows for reducing part of the exposure to the wholesale market and replacing volatile income with contracts linked to stable consumption.
A data center can be powered directly from a renewable energy plant when it's producing, draw from the grid during the rest of the time, and supplement the system with energy storage. For the developer, the result can be a more attractive power purchase agreement (PPA), better utilization of the grid connection, and an increase in overall value.
Continue reading
IPPs are thus moving from competing exclusively to sell electricity to also competing to attract demand .
“There are renewable energy companies with very good structures, people who know the sector and a lot of local contacts. First they got into green hydrogen, then into storage and now they are also entering data centers,” says González-Onieva.
The wall is not energy, but access.
The expansion of data centers clashes with the lack of administrative capacity in the most in-demand nodes.
“Currently, rather than a general lack of physical capacity in the system, there is an administrative backlog due to permits already granted. Spain is still far from its historical peak demand, but a lot of capacity is committed on paper by projects that have not yet been connected,” warns González-Onieva.
Red Eléctrica reported that, since 2022, it has granted 11.8 GW of access capacity on the transmission network for unconnected demand , compared to 7.1 GW previously in service. Unexecuted permits, oversized applications, and tenders at saturated nodes restrict the entry of new consumers.
“In this context, Royal Decree-Law 7/2026 was enacted in March of this year, seeking to release capacity reserved for projects that will not be developed or are speculative. The new capacity reservation fee could significantly increase the DEVEX (or development cost) of large projects, leading some developers to relinquish their permits, reduce the granted power, or put their projects up for sale.”
The result is a growing premium for projects that already combine land, permits, and power.
“Not all megawatts are worth the same. In prime areas, land with potential has a very high value. Outside of these consolidated markets, the commercial risk increases and it will be essential to have an operator or end customer committed to the project,” he argues.
Aragon gains ground on the new digital map
Madrid maintains its leadership in connectivity, operators, and low latency, while Barcelona faces greater land restrictions. Other areas, however, are gaining ground due to their territorial capacity and administrative efficiency.
“Aragon is probably the region that will grow the most because the Government has positioned itself very favorably and has facilitated the development of the projects,” says González-Onieva.
Aragon's General Interest Plans allow for the centralization of some territorial and urban planning procedures, the adaptation of land uses, and the coordination of the infrastructure necessary for these large-scale projects. Under this framework, the Microsoft campuses in La Muela, Villamayor de Gállego, and Zaragoza, the AWS expansion across five sites, and projects such as the 150 MW campus in La Puebla de Alfindén, Green IT Aragón, and Rhodes in Calatorao are progressing.
Surface availability is crucial: a 100 MW data center may require between six and ten hectares.
“The tools that allow for changes in land use, centralize processing, and support development are fundamental for these megaprojects,” he emphasizes.
Artificial intelligence opens new poles
Colocation centers need proximity to major connectivity hubs to reduce latency. AI-focused facilities, on the other hand, prioritize power, floor space, and speed of execution.
“Data centers linked to artificial intelligence need more computing power, but they don't necessarily require such low latency. For these projects, it makes more sense to move away from prime locations and look for sites with more abundant and affordable land, provided there is sufficient electrical capacity and adequate connectivity,” explains González-Onieva.
The change expands opportunities for Aragon, Toledo, Extremadura, Malaga and various regions in northern Spain, although access to electricity and land alone do not guarantee viability.
“Having land, power, and permits is essential, but the project's viability will also depend on attracting an operator or end customer. That's why incorporating a commercial strategy from the early stages can make all the difference.”