360Energy , an Argentine company specializing in the development, construction and operation of solar energy projects, announces the issuance of R$ 255 million in infrastructure “debêntures” in the Brazilian capital market, in a transaction led by Banco Santander Brasil.
Under the project finance scheme, the repayment of the financing is based primarily on future cash flows generated by the projects themselves, backed by long-term energy supply contracts signed with clients in the industrial sector.
The funds will be used to partially finance four photovoltaic solar power generation projects associated with supplying energy to Stellantis Group plants in Brazil, where Fiat, Jeep, Peugeot, and Citroën vehicles are manufactured. These projects include the 13.4 MW Porto Real photovoltaic solar park (PSF) with an installed capacity, scheduled to begin commercial operation in October 2026; and PSF 360E
Goiana I, the largest project developed to date by the company in that country, with 55.5 MW; PSF Goiana II with 6 MW; and PSF 360E Betim, with 18 MW of power. In total, the investment allocated to the construction of these plants exceeds R$ 330 million.

The four projects have an installed capacity of over 90 MW and an estimated annual generation of 187.5 GWh, which will prevent the emission of 77,000 tons of CO₂ per year. Furthermore, during peak construction, the projects employ more than 740 direct and indirect workers, with local labor participating in each of the regions where they are being developed.
A model for self-generation of energy
The investment was structured under an innovative energy self-production model that combines different technologies: mobile structures (trackers), fixed structures on roofs of industrial buildings (rooftops) and structures on vehicle parking surfaces (carports), taking advantage of existing surfaces to generate renewable energy at the consumption site.
Júlio Meirelles, Head of Project Finance at Santander Brazil, highlights: “This is the first long-term, large-scale project we are aware of for a self-generation energy project in Brazil under the inside-the-fence model, in which the photovoltaic park is installed within the energy consumer's own facilities.”
Typically, this type of investment is made by the energy consumer themselves, who must provide the necessary capital for the project's construction. Under the "Energy as a Service" model, 360Energy offers an alternative solution tailored to each client's needs: it handles the design, development, construction, commissioning, and operation of solar assets, including hiring personnel and leasing the necessary equipment.
In this way, customers can access clean and predictable energy generated on their own premises, advance their decarbonization strategy, and achieve energy cost efficiency without needing to allocate capital or assume the risks associated with building and operating a project. Furthermore, the model reduces exposure to risks related to grid connection, especially curtailment, which, according to Meirelles, has been a “limiting factor for the expansion of renewable energy in the country.”
Regarding this, Vanina Mosquera , Corporate Finance Manager at 360Energy, shared: “This issuance represents a milestone for 360Energy and an important step in consolidating our operations in Brazil. Accessing the Brazilian capital market with an entity like Santander allows us to diversify our sources of financing and continue driving large-scale renewable generation projects, supporting the energy needs of our industrial clients.”
Brazil has established itself as one of the leading solar energy markets in Latin America, driven by the high availability of solar resources, growing energy demand, and the need for more sustainable solutions. In this context, 360Energy continues to expand its operations and develop renewable generation solutions that meet the energy needs of industry and contribute to the region's energy transition.