Four companies are competing for the advance purchase of seven single-phase transformers for AMBA I , the Argentine electricity transport expansion project that will require an estimated investment of 800 million dollars and whose main concession will receive bids on December 14.
Siemens Energy (Uruguay), Chint, Faraday SAICyF (Argentina) and Leveltec SA.-TBEA are participating in the call for a supply of approximately 55 million dollars , destined for the future Plomer Transformer Station (ET).
The competition has two options: Siemens Energy and Faraday are bidding for four phases, three phases or all seven units, while Chint and Leveltec-TBEA are only bidding for the complete package.
The contract corresponds to a prior and independent stage of the concession to build and operate AMBA I, which comprises 270 kilometers of 500, 220 and 132 kV lines and will allow the incorporation of around 2000 MW of supply capacity in the Buenos Aires Metropolitan Area.

The equipment must comply with Transener 's technical specifications, with a voltage ratio of 500/√3 – 231/√3 – 34.5 kV and a nominal power of 285/285/16.67 MVA .
Its configuration will allow for the creation of two three-phase banks of 855 MVA each , comprised of three single-phase units. The seventh transformer will function as a shared reserve in case of failures.
The scope of the contract includes the manufacture of the devices, a batch of essential spare parts and technical supervision during assembly and commissioning in Plomer.
Of the $110 million available , half will finance the transformers and the remaining $55 million will be used as an advance to begin construction of the infrastructure.
Once the main concession has been awarded, CAMMESA will transfer the supply contract free of charge to the successful bidder , who will assume the import procedures, the safekeeping of the equipment after its nationalization and the land transport to Plomer.
Furthermore, the value of these assets will not be included in the investment base used to calculate the remuneration of the future concessionaire .
In parallel, the main AMBA I tender has the initial opening of proposals scheduled for December 14, 2026 , with an award projected for early 2027, subject to compliance with the administrative procedures.
The procedure includes the pre-award of the most competitive economic proposal, although the formalization of the contract will be subject to prior approval in the Incentive Regime for Large Investments (RIGI).
Why is it tied to RIGI? The Argentine government is looking to move forward with further network expansions before the deadline for submitting projects to RIGI, scheduled for July 9, 2027. However, the launch of the next calls for proposals will depend on the outcome of AMBA I.
What else is expected from AMBA I?
The competition between Siemens Energy, Chint, Faraday and Leveltec-TBEA will have a new chapter on December 4, when the prices offered for this process will be revealed. This process concentrates the first contracting of high-power equipment linked to AMBA I, with seven units destined for the Plomer substation and advance financing of 55 million dollars.
While for the concession of the transmission work, prospective interested parties must express the Total COP Remuneration in dollars , with updates linked to the Producer Price Index (PPI), published by the Bureau of Labor Statistics of the United States.
Remuneration may extend up to seven years from the commissioning of each stage , while the recovery of the investment will be associated with the COP Tariff applied to transport and/or distribution users identified as beneficiaries.
However, the Maximum COP Remuneration and the Maximum COP Rate still need to be published by circular , so two economic references necessary to close the bids remain pending.