In August, nine BESS projects totaling 327.6 MW simultaneously obtained prior administrative and construction authorization in Spain . A month earlier, batteries already appeared in 42% of the energy files analyzed by Energía Estratégica in the Official State Gazette (BOE) , an acceleration that is beginning to fuel a business parallel to physical deployment: the buying and selling of battery storage positions before they reach construction sites .
International funds, oil & gas companies and large energy groups are tracking advanced stand-alone assets to shorten entry times, especially those close to RTB (ready to build) and with granted access and connection.
Ignacio López Martín , partner and investor at Vida Sustainable Ventures and partner and managing director of Capflex Energía , is also familiar with the evolution of this market from its earliest stages. After the sale of Cable Energía to Shell, which was later integrated into Acciona, a temporary non-compete clause limited his activity in electromobility and led him to explore a segment that was just beginning to develop in Spain at the time: energy storage.
Capflex Energy It was born between the end of 2023 and the beginning of 2024, when there was still no specific framework for batteries and the process for accessing and connecting them wasn't even fully defined. Today, drawing on that experience as a developer, López Martín explains what references are beginning to appear in the buying and selling of assets:

“I have heard of 5 MW projects ranging from 30,000 euros per megawatt to 80,000. In somewhat larger projects on the peninsula, I have heard figures of 100,000 euros per MW and even 120,000 euros per MW.”
They are still far from the peak prices recorded for other renewable energy sources. At the height of buying pressure on solar and wind power, López Martín recalls, transactions reached around 250,000 or 270,000 euros per MW .
The comparison, however, is made on a still young segment with few publicly available references. Enerdatics has recorded 12 storage transactions in Spain since the beginning of 2024, but only three have made any valuation public, and none provide a direct and comparable reference in €/MW . Even recent large-scale acquisitions keep their financial terms confidential.
The deals are, however, starting to gain scale. In March, Aquila Clean Energy sold 80 MW/318 MWh of ready-to-build (RTB) capacity to Return, in what JLL identified as the first transaction of a large-scale BESS portfolio in the RTB stage in Spain. More recently, BW ESS acquired another 126 MW and up to 675 MWh in the Valencian Community, still under development and expected to reach regulatory maturity in 2027.
According to López Martín, demand is concentrated especially on stand-alone installations of at least 100 MW , with advanced permits, secure access, and four- or eight-hour configurations. The problem lies in finding them: below 50 MW there is greater availability, but achieving larger scales is considerably more complex.
One of the constraints arises within the grid itself. A battery needs capacity both to inject and to consume electricity, so a node may have margin on the generation side but not offer enough demand capacity to load the system.
This condition helps to put distance between the large figures announced and the developments capable of progressing to construction.
“The fact that there are 30 GW in the pipeline does not mean that we are going to build 30 GW,” warns López Martín.
Capflex managed around 800 MW of stand-alone projects in the first phase of its portfolio , but the volume is narrowing as new filters are applied. First are the projects that have provided guarantees, secured land, and requested grid access; then, those that actually obtain connection; and only later are those that gather permits, financing, and a sufficient revenue strategy to become buildable assets.
Recent administrative moves also show that hybrid systems are progressing more easily than many standalone developments . Some of the capacity authorized in August relied on existing renewable energy plants and evacuation networks, reducing some of the friction associated with starting from scratch.
In Altarejos, Cuenca, Aitana, Aspe, Bañuela and Turbón, four blocks of 21.69 MW each were added, while Covatillas 3 added another 43.9 MW. In Seville, Afrodita, GES, Don Rodrigo II and Bianor concentrated another 147.17 MW linked to photovoltaic installations.
The path for a stand-alone plant can be different. BESS Solórzano , with 49.738 MW and 199.52 MWh in Cantabria, obtained the prior and construction authorizations, but not the declaration of public utility to resort to expropriation, so it will have to secure land and easements through private agreements.
The photograph thus provides a less spectacular reading than the raw sum of gigawatts, but more relevant for buyers and financiers: under the same pipeline label, assets with very different degrees of maturity and risk profiles coexist .
Continue reading
Being first isn't enough: the bottleneck is funding
The buying frenzy has a temporary explanation. With still limited installed capacity, those who manage to connect first could take advantage of the price differences between off-peak and peak charging times during the initial years. But this opportunity is not permanent: a massive influx of storage capacity would alter the very curve on which arbitrage is currently based.
“Everyone wants the chance to arrive early,” summarizes López Martín.
Buying an advanced pipeline allows large companies to save some of the development years, but having permits, land, and grid access doesn't guarantee that the battery will ever be built. The next hurdle is securing capital.
According to López Martín, there are three main paths today: backing the operation with the balance sheet of a large corporation, having sufficiently predictable regulatory income, or closing long-term contracts with bankable counterparties .
“Until you have all the permits and are RTB [...] no one can talk about really starting to look at how to finance this,” he maintains. Even after that stage is completed, the financier needs to know what cash flow will sustain the debt.
The Spanish market has just provided an initial example of how this equation can be resolved. In July, Grenergy secured €100 million in senior non-recourse financing for Oviedo, a 154 MW, 618 MWh stand-alone BESS plant in Asturias , with Santander and Sumitomo Mitsui Banking Corporation. This transaction followed the company's signing of a ten-year financial tolling agreement with an international investment-grade energy company, a contract that reduces its exposure to purely merchant revenues.
From September 17th, another avenue has emerged. Order TED/966/2026 establishes the peninsular capacity market and opens auctions for generation, storage, and demand. For new investments, service periods will be defined by technology and may extend up to a maximum of 15 years , while bids will be expressed in euros per MW firm per year under a pay-as-bid mechanism.
The new signal expands the options for generating predictable revenue, although crucial parameters are still needed to incorporate it into financial models. Each call for proposals will have to specify, among other things, the firm power requirements, the applicable coefficients for each technology, and the corresponding service periods.
Until those benchmarks gain traction, the difference will remain significant. A utility company can assume greater market exposure and initially finance with its balance sheet; an independent developer needs to demonstrate much earlier where the money to repay the debt will come from.
“I wouldn’t just talk about simplifying”
When Capflex began developing storage solutions between late 2023 and early 2024, batteries were still subject to procedures designed primarily for generation assets. This lack of a specific framework was compounded for part of the period by an additional guarantee of €20,000 per MW , which was later eliminated, while administrative requirements continued to evolve.
For López Martín, the next step is not simply about shortening deadlines, but about differentiating the treatment of a technology with its own characteristics .
“I wouldn’t just talk about simplifying. I would talk about adapting the regulation,” he argues.
The executive cites land use as an example. A 50 MW BESS installation can be deployed on approximately one hectare, including the necessary infrastructure, and located close to the grid connection point, also reducing the length of the evacuation lines. In his opinion, these differences compared to solar or wind farms should be reflected in the permitting procedures.
This regulatory adaptation does not eliminate another structural need: strengthening the grid. López Martín believes that storage can provide flexibility and help spread out some of the necessary investments over time, but it cannot replace them.
“Batteries are a band-aid, not the definitive solution,” he summarizes.
Their argument is that a more robust electrical infrastructure would allow for the integration of larger volumes of generation and new demand, while storage can provide flexibility and buy time during that process.
Thus, the leap forward for Spanish BESS no longer depends solely on obtaining permits. The next stage will be to transform access, regulation, and projected revenue into projects capable of securing financing and becoming operational.