September brought more than just a new batch of energy projects in the Official State Gazette . The monitoring carried out by Energía Estratégica showed how batteries began to occupy an increasingly larger space within renewable energy portfolios just as two regulatory changes addressed two of their main bottlenecks: the time required to reach the construction phase and the possibility of generating long-term revenue once operational .
The mapping identified ten projects directly linked to BESS systems during the month , with at least 334.8 MW of storage capacity explicitly identified . This figure fell short of the actual volume involved because the Larral Hybridization project in Zaragoza and the Greencar 3 project in Carmona did not specify the size of their respective modules in the publications analyzed.
The picture broadened even further when considering technological combinations. Adding the Salinas I, II, and III wind turbine modules, designed to be integrated with photovoltaic generation in Cuenca, brought the total number of projects related to storage or new hybrid configurations to 13 in September.
And there was an earlier sign. On August 31, the Frontones Phase II project was published, another 20 MW BESS in Albacete intended to expand an Elawan complex that already combined wind, solar, and storage. If this project was included in the analysis of the new wave, the known battery capacity reached 354.8 MW . It wasn't just about more megawatts on paper.

The composition of those announcements showed a change in strategy: a significant portion of the developers no longer sought to develop an isolated battery from scratch, but to add it on top of assets that had generation, permits, access or electrical infrastructure already developed .
Fewer months to reach the market and a second piece to sustain revenue
Two regulatory moves coincided behind that advance.
The first one had begun before September with Royal Decree 997/2025 . Its article 6 and its second final provision had created a simplified route for certain battery systems installed within the polygon of projects that already had a favorable environmental declaration.
The modification avoided a new simplified environmental impact assessment for those modules and halved the timeframes for prior administrative authorization and construction administrative authorization .
The effect began to be seen in the advertisements themselves.
In Valladolid, Solaria-Tordesillas II had submitted a 19.993 MW module for public comment through a simplified procedure. In the same province, Pegaso had moved forward with another 31 MW using the same method. Days later, BESS Hibridación Virgen de Areños III , with 35 MW in Palencia , followed suit.
The incentive proved especially relevant for hybrid systems. Where a renewable energy plant already existed with some of the environmental and electrical work already completed, adding batteries no longer necessarily meant starting all over again.
Frontones Phase II had anticipated this logic. Elawan proposed adding 20 MW BESS to a development that already integrated 50 MW of wind, 26.25 MW of photovoltaics, and 4 MW of storage , deepening a multi-technology configuration that Energía Estratégica had already identified within its portfolio under review.
But September added a second variable that did not affect permits, but rather the future economics of the projects.
The publication of Order TED/966/2026 formally created the capacity market of the peninsular electricity system and opened a new remuneration option for assets capable of providing firm power.
For BESS, the signal did not replace arbitrage or their participation in adjusting services. It added another potential revenue stream and, especially for new investments, incorporated the prospect of longer-term contracts within an architecture designed to reward availability.
There were still relevant variables to finalize, including the firmness coefficients that would determine how much recognized capacity each technology would have and other parameters necessary to translate the mechanism into concrete numbers.
Even so, the regulatory mix changed the landscape in two different ways: the Royal Decree sought to reduce the time and administrative cost of certain developments, while the capacity market began to build an additional economic benchmark for its operational stage .
September was the first month in which both trends could be read practically simultaneously within the map of new files.
Andalusia retained the largest scale BESS project, while Castilla-La Mancha deepened the hybridization process.
The geographical distribution revealed three main hotspots.
Andalusia accounted for the largest BESS development identified during the period. BESS FV La Puebla 3 , in Cerro de Andévalo, Huelva, had applied for the necessary permits to add 150.8 MW of battery storage to the solar installation of the same name. This alone represented nearly half of all the storage capacity quantified in the September announcements.
Continue reading
In Carmona, BESS Rey III Solar also appeared, with 35.12 MW , while Greencar 3 began the modification of its authorizations to incorporate batteries into the existing hybrid installation, although the announcement did not specify the new power.
The community also showed activity outside this segment. PSF Puerto Real , with 133.57 MW of photovoltaic capacity , obtained prior administrative authorization, construction authorization, and a declaration of public utility in Cádiz.
Castilla-La Mancha presented a different composition. There, the search for combinations of renewable assets predominated.
In Cuenca, the Bañuela and Turbón modules each added 21.69 MW of BESS to photovoltaic plants of nearly 50 MW. Castillo Garcimuñoz added another 19.5 MW to a complex that combined a 25.5 MW wind farm and a 20.925 MW solar plant.
The same territory concentrated the three Salinas developments, with 36 MW wind modules projected to complement 43.896 MW photovoltaic installations, while Albacete had registered environmental actions on the Breña, Cerroblanco, Torviscal and Majales hybridizations.
The pattern showed that the portfolio transformation was not limited to placing batteries behind a solar plant. Projects also progressed that sought to combine different production profiles to better utilize the grid connection point and extend the hours during which the asset could contribute energy to the system .
Castilla y León completed the triangle of greatest activity.
In addition to the Solaria-Tordesillas II, Pegaso, and Virgen de Areños III solar thermal power plants, the region submitted several major generation projects. In Burgos, Solaria's Eclipse Solar project reached 99.935 MW of photovoltaic capacity , while Vientos del Cid I submitted another 78 MW of wind power for public comment.
The BOE had also incorporated during the period modifications and corrections on Elawan Olmedo I and II , two solar power plants located in Valladolid.
Aragon lagged behind in terms of known BESS volume, although it did register the environmental assessment of the Larral Hybridization project in Zaragoza. There, the size of the battery module was not detailed in the announcement, so it could not be included in the monthly power calculation.
The territorial analysis thus revealed two parallel movements: while Andalusia concentrated larger projects, Castilla-La Mancha and Castilla y León more clearly demonstrated the reuse of existing renewable assets to incorporate new technologies .
While battery production accelerated, the BOE continued to remove projects from the portfolio
The increase in storage coexisted with another trend that had already appeared in previous surveys by Energía Estratégica.
The BOE continued to function as a filter between a much larger theoretical portfolio and the projects capable of maintaining their administrative course.
During September, five renewable developments totaling 401.9 MW were excluded due to rejections or withdrawals .
The largest was Alto Cabrera , a 144 MW wind farm planned by Enel Green Power between León and Ourense. Its prior administrative authorization had been rejected.
In Galicia, Satrebares was added, with 125 MW of wind power , while Aragon registered the fall of the photovoltaic plants Tara , of 23.7 MW, and Umiko , of 46.5 MW, both planned in Tauste.
In Cádiz, the developer of Taraguilla , with a capacity of 62.7 MW , decided not to continue with the wind farm.
The contrast ultimately defined the month.
While some of the renewable energy portfolio continued to lose projects along the way, those seeking to add storage or combine technologies found new ways to advance on already developed infrastructure .
Therefore, September didn't just bring more BESS (Basic Energy Savings System) to the pages of the BOE (Official State Gazette). It revealed a portfolio that was beginning to change its composition: less focused exclusively on adding new generation and increasingly oriented towards leveraging already developed megawatts, making their production more flexible, and extracting more value from existing connection points .