Peru's Ministry of Energy and Mines (MINEM) announced that, in the second quarter of the year, through the Private Investment Promotion Agency (Proinversión) , it will hold a tender for 8 transmission projects of the National Interconnected Electric System (SEIN) , for an investment amount exceeding USD 675 million.
This portfolio of projects is part of the 2025-2034 Transmission Plans, which will be implemented in various regions of the country, and aims to strengthen the reliability of the electrical system, improve the quality of service and guarantee the timely supply of energy for the benefit of thousands of Peruvians.
The execution of works will allow for the expansion of electricity transport capacity, reduce the risk of congestion in the networks and support the growth of energy demand in strategic areas of the country, contributing to the economic and social development of the regions.
The projects have been organized into two groups: the first includes works in the regions of Piura, Lambayeque, Junín, Ayacucho and Cusco:
- 500 kV Miguel Grau Pariñas Link and SE Pariñas 500/220 kV, expansions and associated substations;
- 220 kV Felam Tierras Nuevas Salitral links, expansions and associated substations (ITC Project);
- New Palián 220/60 kV substation and associated 220 kV and 60 kV links (ITC Project);
- 220 kV Muyurina Mollepata link, expansions and associated substations (ITC Project).
- 500 kV Link Bicentenario Chilca Collector, expansions and associated substations;
- 220 kV Tintaya Nueva Nueva San Gabán link, expansions and associated substations;
- 220 kV Nueva San Gabán Puerto Maldonado link, expansions and associated substations (ITC Project);
- 138 kV San Román Yocara Maravilla Link (Juliaca), expansions and associated substations (ITC Project).