Honduras exceeds 1000 MW of installed renewable capacity , according to the 2025 Firm Power Definitive Report prepared by the National Dispatch Center (CND) .
Although state-owned hydroelectric projects are the main contributors of firm power, renewable development in the country is driven by a wide range of private companies .
ENEE leads the hydroelectric segment with plants such as El Cajón (245 MW), Río Lindo (75 MW), Cañaveral (27 MW) and Patuca III (22 MW) .
These are in addition to contracted projects such as Arenal (38 MW) and Vegona (38 MW) , also recognized as firm power.

In the private sector, notable players include CISA (La Esperanza, 8.88 MW) , ENERGISA (Babilonia, 1.67 MW) and SEMSA (Mezapa, 1.43 MW) , along with dozens of small hydroelectric plants contracted or operating on a market basis.
These plants provide firm power validated by the CND, which allows them to participate in dispatch during critical system hours.
In wind power generation, the main developments are Cerro de Hula (124 MW), operated by Energía Eólica de Honduras SA (EEHSA), and San Marcos (112.5 MW), by San Marcos Wind Energy SA .
Chinchayote (12.1 MW) is also listed.
Although these parks represent most of the national wind power capacity, their contribution of firm power is very low , given their variability and current technical criteria.
The solar photovoltaic segment is led by developers such as SERSA (Choluteca I and II, 50 MW) , PRODERSSA (Nacaome, 44.5 MW) , FOTERSA (Solar del Pacífico, 20 MW) , LLANOSUR (Llanos del Sur, 14.8 MW) and GENERSA (Helios, 11.2 MW) .
Although they have significant installed capacity, most of these plants do not provide significant firm power , due to intermittency and lack of backup.
According to the official CND chart, renewables represent around 65% of daily generation .
Of that total, hydroelectricity contributes about 42% (25% regulated and 17% run-of-river), followed by wind power (13%) and solar power (10%) .

Wind farms total 159.75 MW in operation , with outstanding developments such as the Toabré Wind Farm (56.35 MW) , Rosa de los Vientos and Nuevo Chagres .
In these cases, private investment also prevails, with technical returns ranging from 22% to 85% , reflecting operational differences between the various agents.
In contrast, despite totaling more than 600 MW licensed, solar projects do not contribute generation to the system.
All registered parks, including Solar Fotovoltaica Penonomé (120 MW) , La Esperanza Solar (20 MW) or Macano Solar (4.75 MW) , are listed with a current power of zero.
This underutilization exposes a gap between the enabled potential and the actual deployment of infrastructure.
In parallel to this reality, Honduras is moving forward with an international tender to incorporate 1500 MW of firm capacity , with priority given to renewable technologies and storage solutions.
The call, led by the National Electric Energy Company (ENEE) with the support of the Electric Energy Regulatory Commission (CREE) , has already attracted the interest of at least ten international companies, marking a turning point for the sector.
"There are many strong companies interested," Commissioner Wilfredo Flores previously revealed to Energía Estratégica.
The structure of the process, based on reverse auctions and long-term contracts, seeks to increase the country's energy security, improve technological diversification, and attract new players to the local market.
The tendered portfolio includes renewable generation with and without storage, firm technologies and plants with immediate dispatch capacity, all under contracting schemes that seek to guarantee constant availability between 2026 and 2030 .
This redesign responds to a structural need of the system: to incorporate backup power and supply energy deficits without depending on thermal generation.
To be recognized as firm, projects must meet the CND criteria.
The regulation enables an alternative method for those integrating storage: they can choose between the average generation during critical hours or the conventional calculation, depending on which is more favorable for them.
Honduras' renewable energy map is made up of a strong state core and dozens of private companies that lead the development of wind, solar and hydroelectric power , although the weight of firm power remains in the hands of ENEE.
The 1500 MW tender could modify that configuration, incorporating more flexible assets and new players that manage to meet the technical requirements.
With hydroelectric, wind and solar power contributing more than 65% of daily generation , the challenge now is not only to increase installed capacity, but to ensure that renewables can deliver energy consistently and reliably .
Success will depend on technical adaptability and new investments in clean, backed-up solutions.
Power Plant / Project Technology Company / Commercial Status Capacity (MW) Type El Cajón Hydroelectric Owned by ENEE 245.49 Firm Capacity Río Lindo Hydroelectric Owned by ENEE 75.59 Firm Capacity Arenal Hydroelectric Contract 38.2 Firm Capacity Vegona Hydroelectric Contract 37.97 Firm Capacity Cañaveral Hydroelectric Owned by ENEE 27.1 Firm Capacity Shol Hydroelectric Contract 22.63 Firm Capacity Patuca III Hydroelectric Owned by ENEE 21.78 Firm Capacity Cuyamapa Hydroelectric Merchant 10.28 Firm Capacity La Esperanza Hydroelectric CISA (Consorcio de Inversiones SA) 8.88 Firm Capacity Hidro Xacbal Hydroelectric Regional Contract 7.58 Firm Capacity Chamelecón Hydroelectric Contract 4.77 Firm Capacity Rio Blanco Hydroelectric Merchant 2.6 Firm Capacity Coronado Hydroelectric Contract 2.44 Firm Power Cuyamel Hydroelectric Contract 1.9 Firm Power Sazagua Hydroelectric Contract 1.69 Firm Power Babilonia Hydroelectric ENERGISA 1.67 Firm Power Pencaligue Hydroelectric Contract 1.62 Firm Power Mezapa Hydroelectric SEMSA 1.43 Firm Power San Juan Pueblo Hydroelectric Contract 1.25 Firm Power Cortecito Hydroelectric Contract 1.18 Firm Power San Martín Hydroelectric Contract 1.06 Firm Power Matarras Hydroelectric Contract 1.05 Firm Power Nacaome Hydroelectric No Contract / Nor Merchant 0.69 Firm Power Rio Betulia Hydroelectric Contract 0.69 Firm Power Morjas Hydroelectric Contract 0.67 Firm Power La Aurora Hydroelectric Contract 0.65 Firm Power Genera Los Laureles Hydroelectric Contract 0.64 Firm Power Zinguezapa Hydroelectric Contract 0.62 Firm Power Las Glorias Hydroelectric Merchant 0.5 Firm Power Mangungo Hydroelectric Merchant 0.4 Firm Power Churune Hydroelectric Contract / Merchant 0.36 Firm Power Cececapa Hydroelectric Merchant 0.28 Firm Power Agua Verde Hydroelectric Contract 0.23 Firm Power San Alejo Hydroelectric Contract 0.2 Firm Power Chachaguala Hydroelectric Contract 0.2 Firm Power Rio Quilio Hydroelectric Contract 0.16 Firm Power Rio Guineo Hydroelectric Contract 0.15 Firm Power Zacapa Hydroelectric Merchant 0.11 Firm Power Hidro Yojoa Hydroelectric Contract 0.06 Firm Power Los Laureles Hydroelectric Contract 0.05 Firm Power Nispero II Hydroelectric Contract 0.03 Firm Power Cerro de Hula Wind Energy of Honduras, SA (EEHSA) 124 Installed San Marcos (Plant) San Marcos Wind Energy, SA de CV 112.5 Installed Chinchayote Wind CERRO HULA SAN MARCOS CHINCHAYOTE 12.14 Installed Eneresa (w/ Batteries)* Solar ENERESA 2.72 Installed Choluteca I and II Solar Renewable Energy Solutions, SA de CV (SERSA) 50 Installed Nacaome / Nacaome II Solar Solar Production of Solar Energy and Other Renewables (PRODERSSA) 44.5 Installed Pacific Solar FOTERSA (Renewable Energy Solutions*) 20 Installed Llanos del Sur Solar Llanos del Sur Photovoltaic, SA de CV (LLANOSUR) 14.81 Installed FOTOSUR Southern Photovoltaic Solar PV 12.12 Installed Helios Solar Helios / Energy Generations SA (GENERSA) 11.25 Installed ENERSOLSA Enersolsa Solar PV 6.25 Installed Las Lajas Solar Las Lajas (cited as owner in fault reports) 0 Installed Marcovia Solar Comercializadora de Electricidad Centroamericana (CECHSA) 0 Installed Cinco Estrellas Solar ECSA 0 Installed Pavana Solar Solar Energía Básica SA (ENERBASA) 0 Installed