RWE and KKR finalized an investment of approximately 12 billion pounds sterling to develop Vanguard West and Vanguard East , two offshore wind farms that will add 2.8 GW of capacity to the UK electricity system and are scheduled to be fully operational by 2030.
The agreement envisions a joint venture with 50% stakes for each company , backed by the largest non-recourse project financing ever recorded for British offshore wind. Both projects will have the capacity to supply electricity equivalent to the consumption of approximately three million homes.
The operation includes the financial closing of the two facilities and the participation of 35 international banks , in a structure that combines private capital, institutional financing and public resources.
The projects will be located in the North Sea, between 50 and 80 kilometers off the coast of Norfolk, in East Anglia. Each park will have 1.4 GW of installed capacity , making it one of the largest offshore developments in the country.

Markus Krebber , CEO of RWE, emphasizes that the alliance represents a sign of confidence in the British market and its energy investment prospects.
"Our strategic partnership with KKR provides a solid foundation for the joint execution of Vanguard West and Vanguard East," Krebber said, according to the translation of his official statement.
The executive believes that the financial structure achieved supports the viability of both developments and allows progress to the next construction phase.
It also states that obtaining "the largest project financing in the history of UK offshore wind" demonstrates the confidence of financial institutions in the initiatives and the execution capabilities of the companies.
The partnership was initially announced in January 2026 and was formalized through KKR's acquisition of a 50% stake in each project.
Both companies will jointly undertake the development, construction and operation of the parks, while RWE will lead their execution on behalf of the joint venture .
Financing from 35 banks and participation from the National Wealth Fund
One of the main elements of the operation is the mobilization of financial resources to support the construction of the complexes and their transmission infrastructure.
The financial closing comprises £11.1 billion in cash-available funding lines and £1.7 billion in ancillary lines , provided by a consortium of 35 international entities.
These facilities are financing instruments and should not be confused with the total investment budget of approximately 12 billion pounds.
The scheme is highlighted by the commitment of £1 billion from the National Wealth Fund , the British public bank focused on mobilizing investments in strategic sectors.
This is the first time this organization has participated in financing offshore wind projects of this kind and represents its biggest commitment to the sector to date.
The structure also incorporates credit guarantees from Euler Hermes of Germany and EIFO of Denmark , intended to support financial requirements.
Furthermore, the developments have contracts for difference awarded during the seventh UK allocation round, held in January 2026.
Continue reading
Each project was awarded a 20-year contract, indexed to inflation, with an award price of £91.20 per MWh , expressed in 2024 values.
This mechanism allows for the establishment of long-term revenue conditions, a relevant aspect for structuring capital-intensive investments such as offshore wind installations.
Vincent Policard , co-head of European Infrastructure at KKR, points out that the UK has opportunities to develop critical infrastructure, boost economic growth and strengthen security of supply.
"Implementation at this scale requires substantial private investment," Policard stated, according to the translation of his remarks.
The executive maintains that KKR provides long-term capital and international experience to support complex projects during their construction and operation phases.
In that regard, it highlights that the collaboration with RWE demonstrates how private financing can contribute to materializing energy infrastructure capable of supplying around three million homes.
Construction from 2027 and commissioning in 2030
In terms of execution, the preparatory work on land is already at an advanced stage of development , especially the activities related to cable laying and the construction of substations.
The schedule states that the marine works will begin in early 2027, while the installation of the first foundations of Vanguard West is planned for the first half of that year.
Vanguard East will then advance, with the goal of completing the commissioning of both parks in 2030 .
The facilities will share coordinated connection infrastructure to reduce environmental impacts and impacts on communities in the region.
Krebber says that the preparatory progress puts the joint venture in a favorable position to begin offshore activities according to the established schedule.
"The projects will strengthen national electricity generation," says the CEO, who links the new power to the resilience of the system and energy security.
The British government estimates that the investment will support more than 2,400 jobs during the construction and operation phases .
British Prime Minister Andy Burnham , for his part, believes the deal is a sign of confidence in the country's industrial investment opportunities.
"This significant investment in UK renewables is a vote of confidence to build in Britain," Burnham emphasized, according to the translation of his official statements.
The official also emphasizes the importance of public participation in mobilizing private resources and expanding national generation.
"Our National Wealth Fund means that public investment is working alongside private capital," the prime minister maintains.
Thus, the combination of 2.8 GW of new capacity, international financing and 20-year revenue contracts forms the basis on which RWE and KKR will advance the construction of Vanguard West and Vanguard East, with the aim of completing both developments towards the end of the decade.